#3. Which two of the following are true about the Scrum Master role?
- Is the contact point between the team and the customer
2. Manages the Development Team for maximizing the productivity
3. Teaches the Development Team to keep the meetings to their timebox
4. Should be dedicated to one project at a time
5. Works with other Scrum Masters in the organization to adopt Scrum
Solution :
3. Teaches the Development Team to keep the meetings to their timebox
5. Works with other Scrum Masters in the organization to adopt Scrum
Explanation :
The Scrum Master does not manage people, and does not have to be full-time.
The Development Team is self-organized and handles the assignments itself, and measures the performance of the Sprints.
It is the Product Owner’s responsibility to identify what has been done before the Sprint Review, since s/he is the main contact person with the stakeholders.